Main accomplished and current objects of StroyCity in 2010-2024

Комплекс работ по проектированию, изготовлению и монтажу модульных конструкций и пусконаладочным работам
CustomerGazprom Neft Shelf, LLC
General ContractorStroyCity, LLC
Object name and locationTechnical re-equipment of the water treatment and reservoir-pressure maintenance systems of the Prirazlomnaya offshore ice-resistant fixed platform (phase 1), Varandey, Nenets Autonomous Okrug, Barents Sea
Fulfilment periodAugust 2022 – November 2024
Type of worksSet of operations: modular structures design, manufacture and assembly, as well as commissioning works
Комплекс работ по строительству, монтажу технологических трубопроводов и оборудования, пусконаладочные работы
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationComplex for the production of aromatic hydrocarbons (aromatics production complex), phase 3.1, section 300, located on the territory of Gazpromneft Omsk Oil Refinery, JSC
Fulfilment periodAugust 2022 – February 2025
Type of worksSet of operations: construction and assembly of process pipelines and equipment, commissioning works
Устройство технологических трубопроводов (сети ВиК, теплосети, основные строительно-монтажные, механо-монтажные, пусконаладочные работы)
CustomerGazprom-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationEffluent facilities of Gazprom-ONPZ, JSC. Mechanical cleaning unit, Off-site utilities
Fulfilment periodJune 2021 – November 2023
Type of worksInstallation of process pipelines (water supply and sewerage networks, heating networks, basic construction and installation, mechanical installation, commissioning)
Очистные сооружения
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and location“Effluent treatment facilities. Tank blocks. Substructures” situated within the territory of the operating plant Gazpromneft-ONPZ (JSC)
Fulfilment periodNovember 2018 – November 2023
Type of worksComplex of construction and assembly works and start-up procedures on a turnkey basis of three tank farms; tanks volume range of 100 m3-20 000 m3.
Монтаж резервуаров
CustomerGazprom-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationReconstruction of the delayed coking unit 21-10/3М (2nd and 3rd stages) (preparation period) (DCU)
Fulfilment periodAugust 2020 – October 2022
Type of worksMounting tanks, process pipelines, equipment, corrosion protection of the process pipelines, changing and laying water supply and sewerage pipelines, general construction works
Общестроительные работы, монтаж металлоконструкций и оборудования
CustomerGazprom-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationReplacement of motor truck scales in the equipment fleet
Fulfilment periodOctober 2021 – July 2022
Type of worksGeneral construction works, erections of metal structures, and equipment assembly
Монтаж технологических трубопроводов
CustomerGazprom-ONPZ, JSC
General ContractorNIPIGAZ, JSC
Object name and locationComplex or repair and installation works in accordance with the accepted engineering solutions for the heating of Interconnecting Utilities (projects of the Large-Scale Project Directorate) on the pipe racks TK5 and TK5.1, on the lines 1219,1222, sections TK5.1-TK-12-TK-16 of the line LC-1211, within the framework of the project “Construction of off-site facilities of the CDU-VDU Complex, DCU and DCC within the territory of the working factory of Gazpromneft-ONPZ JSC” (COR 189_2, COR 189_3, COR 310)
Fulfilment periodAugust 2021 – October 2021
Type of worksProcess pipeline installation
Замена технологических трубопроводов
CustomerGazprom-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationRepair and replacement of engineering utilities at the off-site facilities, Technical Control Laboratory, Chief Power Engineer Department, Administrative Economic Department and Commercial Production Department
Fulfilment periodMay 2021 – August 2021
Type of worksReplacement of industrial pipelines (engineering utilities and heat distribution network)
Монтаж металлоконструкций, технологических трубопроводов пара, линий конденсата пара, нанесение АКЗ
CustomerGazprom-ONPZ, JSC
General ContractorNIPIGAS, JSC
ContractorStroyCity, LLC
Object name and locationRe-equipment of the intermediate pressure steam piping within the framework of the campaign “Remedial measures complex aimed at the utilization of excess steam from the Advanced Oil Refining Complex considering no consumption by CDU/VDU and delayed coking unit” (stage 1: installation of process pipelines TK2 (section from the motor road 7х28 to 8х28), stage 2: installation of process pipelines TK2 (AD-9/Isomalk-2))
Fulfilment periodFebruary 2021 – July 2021
Type of worksSteel structures assembly, installation of steam process pipelines and steam condensate lines, application of corrosion protection coating
Комплекс строительно-монтажных работ
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationTechnical re-equipment and partial replacement of the Aromatic Hydrocarbons Production Complex (KPA) (to insure the acceptance of benzene concentrate L-35/11-600), Gubkina Ave, 1
Fulfilment periodJuly 2020 – November 2020
Type of worksConstruction, assembly and commissioning works on site
Лабораторно-аналитический комплекс
CustomerGazpromneft – Catalytic Systems, LLC
General ContractorStroyCity, LLC
Object name and locationLaboratory and Analysis Complex, key production facilities and off-site facilities within the territory of the operating plant. Works in the Catalyst Testing Engineering Center
Fulfilment periodJune 2020 – April 2021
Type of worksComplex of construction and assembly works for the Center construction, including removal of utility networks, lightning pole installation, temporary power supply and utility networks installation
Лабораторно-аналитический комплекс
CustomerGazpromneft – Catalytic Systems, LLC
General ContractorStroyCity, LLC
Object name and locationLaboratory and Analysis Complex, core production facilities and off-site facilities within the territory of the operating plant. Substructure and utilities. Initial-stage works
Fulfilment periodDecember 2019 – February 2021
Type of worksEarthworks, piled foundation works
Переоборудование нефтяных резервуаров Р-15 Р-16 под приём ДТЗ
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationRe-equipping oil tanks P-15 and P-16 for storage of winter diesel fuel for the needs of Gazpromneft-ONPZ, JSC
Fulfilment periodNovember 2019 – June 2020
Type of worksComplex of construction and assembly works and start-up procedures, dismantling and mounting equipment and pipelines
Организация схемы фильтрации СМТ
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationArranging filtering circuit for filtering low-viscosity marine fuel
Fulfilment periodNovember 2019 – May 2020
Type of worksComplex of construction and assembly works and start-up procedures, equipment mounting
Установка сернокислотного алкилирования
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationSulfuric acid alkylation installation (25/12) Facilities No. 2
Fulfilment periodSeptember 2019 – October 2019
Type of worksRepair of process equipment and pipelines during shutdown maintenance
Организация схемы выпуска ТСУ-0,5 Гибрид
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationComplex of construction and assembly works and start-up procedures for the "Thermal power station-0.5 Hybrid output design"
Fulfilment periodJune 2019 – June 2020
Type of worksComplex of construction and assembly works and start-up procedures
Строительство производства катализаторов
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationComplex of construction and assembly works and start-up procedures for the "Checkpoint for the construction site of catalysts production plant"
Fulfilment periodJune 2019 – November 2019
Type of worksComplex of construction and installation works
Исилькуль-ПП
CustomerTransneft-Zapadnaya Sibir, JSC
General ContractorUralStroyNeft, LLC
Object name and locationPipeline remote pumping station "Isilkul-PP" Engineering and technical safety system. Reconstruction
Fulfilment periodApril 2019 – November 2019
Type of worksComplex of construction and assembly works on the vertical stainless steel tanks (РВС -10 000) № 7, 8, 13, 14
Барабинск
CustomerTransneft-Zapadnaya Sibir, JSC
General ContractorStroyCity, LLC
Object name and locationGPHE "08-ТПР-005-011296". Trunk pipeline pumping station "Barabinsk". Construction works.
Fulfilment periodApril 2019 – September 2019
Type of worksConstruction and assembly works
08-ТПР-004-006995
CustomerTransneft-Zapadnaya Sibir, JSC
General ContractorStroyCity, LLC
Object name and locationGPHE "08-ТПР-004-006995". The automation system of oil metering station No. 448. Omsk Regional Oil Pipeline Management. Omsk pipeline remote pumping station. Technical re-equipping.
Fulfilment periodApril 2019 – October 2019
Type of worksTechnical re-equipping the automation system of oil metering unit
08-ТПР-005-023024
CustomerTransneft-Zapadnaya Sibir, JSC
General ContractorStroyCity, LLC
Object name and locationGPHE «08-ТПР-005-023024». Replacement of trunk pipeline station at the pipeline remote pumping station «Isilkul-PP» Kurgan oil pipeline management office. Technical re-equipping. GPHE «08-ТПР-005-023025». Leaks and drainage collecting and pumping system at the pipeline remote pumping station «Isilkul-PP». Kurgan oil pipeline management office. Technical re-equipping.
Fulfilment periodMarch 2019 – October 2020
Type of worksTrunk pipeline station replacement. Leaks and drainage collecting and pumping system
Л-35/11-600
CustomerGazpromneft-ONPZ, JSC
General ContractorNeftekhimremont, LLC
Object name and locationReconstruction of catalytic reforming unit L-35/11-600
Fulfilment periodAugust 2018 - April 2019
Type of worksDismantling and installation works
Лабораторно-аналитический комплекс
CustomerGazpromneft – Catalytic Systems, LLC
General ContractorStroyCity, LLC
Object name and locationLaboratory and Analysis Complex, core production facilities and off-site facilities on the territory of the Gazpromneft-ONPZ (JSC) operating plant
Fulfilment periodAugust 2018 – June 2019
Type of worksDisassembly of building structures, underground utilities and metal structures. Complex of construction and assembly works and start-up and commissioning operations
ЗМУО. Производство № 2. Модернизация здания объединенной операторной № 1(ЖМ № 8455)
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationReplacement of outmoded equipment. Facilities No. 2. Upgrading the building of the combined operator room No. 1 (ZhM No. 84455)
Fulfilment periodJuly 2018
Type of worksComplex of construction and assembly works and start-up procedures, equipment and C&I mounting
Объекты общезаводского хозяйства
CustomerGazpromneft-ONPZ, JSC
General ContractorNIPIGAZ, JSC
ContractorStroyCity, LLC
Object name and locationOff-plant facilities for the CDU/VDU, DCU and AORC operation on the territory of the Gazpromneft-ONPZ (JSC) operating plant
Fulfilment periodNovember 2017 – December 2019
Type of worksComplex of construction and installation works for the preparation of the construction site and demolition of existing structures, installation of water supply and sewerage networks, piling works
Объекты общезаводского хозяйства
CustomerGazpromneft-ONPZ, JSC
General ContractorNIPIGAZ, JSC
ContractorStroyCity, LLC
Object name and locationOff-plant facilities for the CDU/VDU, DCU and AORC operation on the territory of the Gazpromneft-ONPZ (JSC) operating plant
Fulfilment periodJuly 2018 – July 2019
Type of worksComplex of construction and installation works including corrosion protection of technological pipelines on pipe racks Pipeline tie-in works, repair of pile caps and columns of process trestle, modification of pipe racks
Магистральная насосная перекачивающая станция
CustomerTransneft – Zapadnaya Sibir, JSC
General ContractorStroyCity, LLC
Object name and locationMain pumping station “Barabinsk”, located on the Barabinsk pipeline remote pumping station (Barabinsk, Novosibirsk region)
Fulfilment periodFebruary 2019 – September 2019
Type of worksConstruction and installation works including construction/dismantling of temporary buildings and structures. Exploration of foreign pipelines and nets crossing. On-site testing of diagnostic devices passing ability. Start-up and commissioning operations. Participation in complex testing of systems and equipment.
РВС-10000
CustomerTransneft – Zapadnaya Sibir, JSC
General ContractorUralStroiNeft, LLC
ContractorStroyCity, LLC
Object name and locationVertical Stock Tank-10000 № 9, 10, 11, 12, Omsk District Oil Pipeline Agency, pipeline remote pumping station «OMSK» on the Omsk pipeline remote pumping station (Omsk)
Fulfilment periodMay 2018 – June 2019
Type of worksConstruction and installation works including construction/dismantling of temporary buildings and structures. Exploration of foreign pipelines and nets crossing. On-site testing of diagnostic devices passing ability. Start-up and commissioning operations. Participation in complex testing of systems and equipment
ЗМУО
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationReplacement of worn-out equipment. Connection of pumping technological block-box to water and power supply systems, PCS and turnkey communication networks on the territory of the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodMay 2018 – March 2019
Type of worksDesign and survey works and construction and installation works including reconstruction, modernization and technical re-equipment of the facility. Industrial safety examination, registration of positive safety expert review in Rostekhnadzor, author’s supervision services provision
Временная вертолетная площадка
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationTemporary helipad on the territory of the Gazpromneft-ONPZ (JSC) operating plant
Fulfilment periodJune 2018 – August 2018
Type of worksComplex of construction and assembly works and start-up and commissioning operations on a turn-key basis at three helipads, three parking areas and roads. Landscaping and gardening of the area of 8 hectares using roll and sown lawn
Оборудование магистральной насосной No2
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationOn-spot loading rack-2 on the pipe welding station-2 on the territory of the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodJune 2017 – October 2018
Type of worksDevelopment of the railroad facilities of the enterprise. Construction of non-public railway tracks for the on-spot loading rack-2 at the pipe welding station-2 of Gazpromneft-ONPZ, JSC. Construction of quiescent rail road-track scale at the on-spot loading rack-2 of Gazpromneft-ONPZ, JSC (construction, installation, commissioning works)
Комплекс строительно-монтажных работ
CustomerGazpromneft-ONPZ, JSC
General ContractorGazprom Avtomatizatsiya, PJSC
Object name and locationCDU/VDU complex located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodJune 2017 – July 2019
Type of worksComplex of construction and installation works
Замена резервуара № 779
CustomerGazpromneft-SM, JSC, OZSM
General ContractorStroyCity, LLC
Object name and locationTechnical re-equipping. Renewal of reservoir No. 779 in the depot No. 1131. Unit No. 37/1-4” in the branch plant of Gazpromneft-SM, LLC, OZSM located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodJune 2017 – December 2017
Type of worksDismantling, assembly, construction, insulation, chemical protection, electrical installation works, external water and sewerage lines and wastes disposal
Замена резервуаров № 854, 855
CustomerGazpromneft-SM, JSC, OZSM
General ContractorStroyCity, LLC
Object name and locationTechnical re-equipping. Renewal of reservoir No. 854, 855 in the depot No. 193, reservoir No. 883 in the depot No. 1133 TF-3 in the branch plant of Gazpromneft-SM, LLC, OZSM
Fulfilment periodJune 2017 – December 2017
Type of worksDismantling, assembly, construction, insulation, chemical protection, electrical installation works, external water and sewerage lines, control and measuring devices and automatic equipment, process control system, and wastes disposal
Оборудование магистральной насосной No2
CustomerTransneft – Zapadnaya Sibir, JSC
General ContractorStroyCity, LLC
Object name and locationTrunk pipeline pump station of pipeline remote pumping station “Omsk”. Construction. Equipment for trunk pipeline pump station No. 2. Replacement of main pump units No. 1, 2 and 3. Omsk Regional Oil Pipeline Management. Pipeline remote pumping station “Omsk”. Technical re-equipment located on the Omsk pipeline remote pumping station (Omsk)
Fulfilment periodApril 2017 – November 2017
Type of worksConstruction and installation works (dismantling, installation of pipelines and pumping units) including the construction/dismantling of temporary buildings and structures; diagnostic devices testing; commissioning work including individual and functional testing
Блок очистки газов регенерации каталитического крекинга
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationTreatment unit of regeneration gases of catalytic cracking (works on demolition/dismantling of capital facilities and transfer of out-door plumbing system networks) on the territory of the Gazpromneft-ONPZ, JSC operating plant (Omsk, Gubkin Ave., 1)
Fulfilment periodMarch 2017 – July 2017
Type of worksDismantling of equipment and piping with partial saving of equipment and building constructions (potassing pumping house, foundations, compressor house), ferroconcrete fume stack 100 m high element-by-element (with 2 m rings) using diamond carving and lorry crane Liebherr LTM 1500
«Автоматизированная установка тактового налива No1»
CustomerGazpromneft-ONPZ, JSC
General ContractorOMUS-1, OJSC
Object name and locationAutomated installation of timed pouring No. 1 located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodOctober 2016 – August 2017
Type of worksConstruction of the breast wall device, installation of fire tanks (monolithic bottom slabs, monolithic tank walls), installation of water supply and sewage networks.
«Реконструкция установки 36/1-1 с целью получения масел-мягчителей типа ТDAE» на ООО «Газпромнефть-СМ» «ОЗСМ»
CustomerGazpromneft-SM, LLC, OZSM
General ContractorStroyCity, LLC
Object name and locationReconstruction of installation 36/1-1 for the production of softening oils like IDAE on the Gazpromneft-SM, LLC, OZSM operating plant.
Fulfilment periodSeptember 2016 – December 2016
Type of worksDismantling of existing equipment and buildings, general construction works, mechanical installation works (technological equipment and piping), electrical works, instrumentation and control equipment, plant floor system, pre-commissioning activities, equipment supply.
«Комплекс ЭЛОУ-АВТ» на территории действующего предприятия АО «Газпромнефть-ОНПЗ»
CustomerGazpromneft-ONPZ, JSC
General ContractorOMUS-1, OJSC
Object name and locationCDU/VDU complex located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodMay 2016 – March 2017
Type of worksGround works, pile works, foundation pour, backfill of pit hollows, mantling of water drawdown system.
Демонтажные работы существующей этажерки
CustomerOmskiy kauchuk, PJSC
General ContractorStroyCity, LLC
Object name and locationTechnical re-equipping of carbolic acid/acetone production section 101-105 located in the Omskiy kauchuk, PJSC operating plant.
Fulfilment periodMay 2016 – July 2019
Type of works1. Workshop 101-105.
Demolition of the existing equipment supporting structure and foundation in view of pit excavation. Demolition works of the pump station on the axes 19-24 AB. Construction of new equipment supporting structures and foundations. Ground injection.
Working period: May 2016 – September 2017

2. Control room.
Preparation works (land works, crushed-stone bed and cement bed). Construction of the foundation plate MP-1. Construction of walls and columns. Construction of the floor slab panel MP-1. Installation of blastproof doors.
Working period: October 2018 – July 2019
Благоустройство улицы Ленина
CustomerGazpromneft, JSC
General ContractorPetrostroy, LLC
Object name and locationImprovement of Lenin street on the site from Partizanskaya street to Victory square (including the adjacent Dzerzhinsky square, the Academic Drama Theatre square and the Theatre garden), located at: Omsk, Lenin str.
Fulfilment periodApril 2016 – May 2016
Type of worksInstallation of monolithic structures of stairwells with retaining wallsand monolithic structures of underground pedestrian crossing
Локальный водоблок для обеспечения оборотной водой технологических установок
CustomerGazpromneft-SM, JSC OZSM
General ContractorStroyCity, LLC
Object name and locationLocal water unit for de-asphalting plants 36/1-1, 36/13, and 36/3-4 located at the Gazpromneft-ONPZ, JSC operating plant Gazpromneft-ONPZ, JSC
Fulfilment periodOctober 2015 – December 2016
Type of worksConstruction of pile bases, water supply and sewerage, cooling towers, industrial building, process pipe racks. General construction, electrical installation, construction and installation work. Equipment supply, start-up and commissioning works, installation of ventilation and heating systems, installation of water supply and sewerage networks, process pipelines and equipment installation, automation
ГПП-6Н
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationGPE-6N (construction and installation commissioning activities) located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodApril 2015 – February 2016
Type of worksElectric and general construction works, installation of ventilation and heating system, of water supply and sewerage networks, industrial pipelines and equipment, automation
Реконструкция КТ-1/1. Секции 100/200/300/400.
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationReconstruction of installation CT 1/1 of section 100/200/300/400 on the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodMarch 2015 – September 2015
Type of worksPreparatory works, pile works, ground works, installation of monolithic instrument room, steel constructions installation, finishing works, electrical works, installation of water supply and sewage networks
Портальная смотровая площадка
General ContractorCC IdealStroy, LLC
Object name and locationPortal viewing platform with a stair descent to the embankment of Irtysh river. Chokan Valikhanov str, Omsk.
Fulfilment periodJuly 2014
Type of worksConstruction of monolithic ferroconcrete walls, floor slabs, stair flights. Electrical works
Водоблок для установок ЦВК-4,5
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationWater unit for installations VAC-4 and 5 located at the GazpromneftONPZ, JSC operating plant
Fulfilment periodFebruary 2014 – June 2015
Type of worksPreparatory works, pile works, ground works, installation of concrete and ferroconcrete monolithic constructions, steel constructions and industrial pipelines installation, finishing works, electrical works, installation of water supply and sewage networks, instrumentation and control equipment
Водоблок для установок 43/103
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationWater unit for installations 43/103 located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodАпрель 2014 – декабрь 2015 г.
Type of worksPreparatory works, pile works, ground works, installation of concrete and ferroconcrete monolithic constructions, steel constructions and industrial pipelines installation, finishing works, electrical works, installation of water supply and sewage networks, instrumentation and control equipment
Терминал слива, хранения и закачки в переработку СГК
CustomerGazpromneft-ONPZ, JSC
General ContractorOMUS-1, OJSC
Object name and locationTerminal of gutter, storage and injection into processing of SGC located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodNovember 2013 – December 2014
Type of worksConstruction of piled foundations, monolithic slabs, cable tray systems, WSS, buried tank, retaining wall
Установка Гидрокрекинга ВГО
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationInstallation of hydrocracked VGO on the Gazpromneft-ONPZ (JSC) operating plant
Fulfilment periodOctober 2013 – May 2014
Type of worksDismantling of factory buildings, chimney, process pipe racks, reactor blocks, benches, tank farm, flare
Цех №16. Градирня №5 на водоблоке №5
CustomerGazpromneft-MNPZ, JSC
General ContractorStroyCity, LLC
Object name and locationSection No. 16. Cooler No. 5 on water unit No. 5 located on the territory of the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodOctober 2013 – April 2014
Type of worksConstruction and assembly of cooler steel constructions
Благоустройство территории АО «Газпромнефть-ОНПЗ»
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationPlant office building, site improvements on the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodAugust 2013 – September 2015
Type of worksDecoration works, electrical works, heating radiators and fire alarm system replacement, facade repairing. Construction of underground water supply lines and canalization
Локальный блок оборотного водоснабжения
CustomerOmskiy kauchuk, PJSC
Object name and locationLocal block of water reuse located at the Omskiy kauchuk, PJSC operating plant
Fulfilment periodAugust 2013 – February 2014
Type of worksConstruction of buried catch pit, piled foundations, WSS networks, foundations and flooring
Объекты социально-бытовой сферы. База отдыха им. Д.М. Карбышева
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationObjects of social and domestic sphere. D.M. Karbyshev Recreation Centre. Omsk region, Krasnoyarka village.
Fulfilment periodMay 2013 – May 2014
Type of worksReconstruction of canteen building, bedroom building and club building
Вагонные весы на эстакаде налива тит. 8501 ТСБ-1 для взвешивания ж/д четырехосных вагонов
CustomerGazpromneft-ONPZ, JSC
General ContractorStroyCity, LLC
Object name and locationTrack scales on pouring dock tit. 8501 TSB-1 for weighting four-axle railway wagons located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodApril 2013 – October 2013
Type of worksInstallation of piled foundations, cable tray systems, floodlight towers, railway track and railway scales, landscaping, technological process control
Реконструкция азотно-кислородной станции
CustomerOmskiy kauchuk, PJSC
General ContractorStroyCity, LLC
Object name and locationReconstruction of nitrogen and oxygen station and reconstruction of air separation section on the Omskiy kauchuk, PJSC operating plant
Fulfilment periodDecember 2012 – June 2014
Type of worksConstruction of piled foundation, installation of WSS networks, construction of foundations, steelwork erection, assembling of sandwich panels, brickwork of internal partitions, flooring, landscaping
Автоматическая станция смешения масел производительностью 70 тыс. тонн в год
CustomerGazpromneft-SM, LLC, OZSM
General ContractorOMUS-1, OJSC
Object name and locationAutomatic oil mixture station with a capacity of 70 thousand tons per year located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodAugust 2012 – October 2013
Type of worksConstruction of piled foundations, installation of WSS networks, construction of foundations for tanks and concrete dyking of tanks, landscaping
Установка производства полипропилена
CustomerTobolsk-Polimer, LLC
General ContractorThe Linde Group
SubcontractorOMUS-1, JSC
Object name and locationInstallation of polypropylene production. Discharge zone (CA 31, CA 90) located at «Tobolsk-Polimer» operating plant
Fulfilment periodMay 2012 – May 2013
Type of worksInstallation of foundations, floors, water supply and sewerage networks
Эстакада налива битума в железнодорожные цистерны.
CustomerGazpromneft-ONPZ, JSC
General ContractorNeftekhimremont, LLC
Object name and locationFlyover of bitumen pouring into railway tanks. Installation 19/3 located at the Gazpromneft-ONPZ (JSC) operating plant
Fulfilment periodMarch 2012 – July 2013
Type of worksSite preparation, structures dismantling, utility lines removal, construction works (ground works, installation of foundations, floors, water supply and canalization networks)
Комбинированная установка сероочистки газов, регенерации раствора МЭА и получения элементарной серы
CustomerGazpromneft-MNPZ, JSC
General ContractorOMUS-1, OJSC
Object name and locationIntegrated plant of gases desulphurization, MEA dip regeneration and production of free sulphur located at the Gazpromneft-MNPZ, JSC operating plant (Moscow city, Kapotnya, 2nd sect., bld. 1, block 3)
Fulfilment periodSeptember 2011 – August 2013
Type of worksSite preparation, structures dismantling, utility lines removal, construction works (ground works, installation of foundations, floors, water supply and canalization networks), landscaping
Памятник омичам, внесшим значительный вклад в освоение космоса
CustomerBranch of Federal State Unitary Enterprise M.V. Khrunichev GKN PTs PA Polet
Object name and locationMonument to Omsk citizens, who greatly contributed to space exploration. Omsk city, Kosmicheskiy Ave., 17a
Fulfilment periodNovember 2010 – July 2011
Type of worksGeneral construction and installation works
Комплекс установок гидроочистки бензинов каталитического крекинга и дизельных топлив
CustomerGazpromneft-ONPZ, JSC
General ContractorOMUS-1, OJSC, Genenergomontazh, LLC
Object name and locationComplex of catalytic cracking naphtha and diesel fuels hydrotreater located at the Gazpromneft-ONPZ, JSC operating plant
Fulfilment periodMarch 2010 – June 2012
Type of worksPreparation of the construction site, structures dismantling, utility systems removal, ground works, piling works, installation of concrete and ferroconcrete monolithic constructions and floors, precast ferroconcrete constructions assembly, steelwork erection and cooler construction